Issue 97

Formal title: Meter shortage risk driven by global materials availability and supply chain challenges

Current Status

Submission
Assessment
Closed

Due to a global shortage of materials and the on-going impacts of COVID-19 on global supply chains, there is a shortage of semi-conductors among other crucial components, which impacts the ability of Meter manufacturers to produce Meters. Through engagement with industry colleagues we have become aware that this is impacting on the availability of various types of electricity Meters including those required for Settlement under the BSC. This shortage of Settlement Meters could impact on a number of BSC processes. Our understanding is that this issue is also impacting the availability of Current Transformer (CT) Metering, which has the highest potential for material impact (due to usually being installed at higher consumption/higher voltage sites). Thankfully it is currently our understanding that shortages are not impacting on CVA Metering however we will continue to monitor this.

Progression

Issue 97 was raised by Elexon on 20 August 2021.

The first Issue 97 meeting was held on Tuesday 28 September 2021 where potential mitigations of the meter shortage were discussed.

The second Issue 97 meeting was held on Monday 15 November 2021 where the aggregated impacts reported through RFIs were discussed.

The third Issue 97 meeting was held on Monday 7 March 2022 where the RFI  data was discussed. The Issue was agreed to be closed and Elexon will continue to monitor the Issue and request RFIs from industry so we can publish the data.

 

Next Events

The Issue Report was tabled at the BSC Panel meeting on 12 May 2022.

My BSC

Click on the X next to any of the icons to replace them with a short-cut link to the page you are currently on or search for a specific page.

List of BSC Insights

Previous Circulars

Training videos and services

Market Entry

Charge Codes and Switch Regimes

Add New

×

Or