Issue 88

Formal title: 'Clarification of BSC Arrangements relating to Complex Sites'

Current Status

Submission
Assessment
Closed

It has become clear that there are a number of issues and ambiguities relating to the complex site arrangements, which this issue seeks to address.

Elexon believes that, as a result of the current lack of clarity, different Suppliers and Supplier Agents are likely to be operating with different interpretations of what is permitted under the complex site arrangements. This has the potential to create distortions in the supply market, with certain customers potentially incentivised to take their supply from a Supplier with an interpretation of the rules that favours their own situation.

 

Progression

Issue 88 was raised on 18 March 2020 and three meetings have since been held. A Request for Information was issued following the second meeting on 27 July 2020 and the findings were discussed at the meeting held on 25 November. The latest meetings for Issue 88 were held in April 2021 and the Issue Report was presented to the Panel at its meeting on 10 June 2021.

Next Events

Issue 88 is now closed.

My BSC

Click on the X next to any of the icons to replace them with a short-cut link to the page you are currently on or search for a specific page.

List of BSC Insights

Previous Circulars

Training videos and services

Market Entry

Charge Codes and Switch Regimes

Add New

×

Or