CP1496: Data flows

Introduction of two new dataflows for Commissioning in the Metering System process for LDSOs, Suppliers and MOAs. Use of Data Transfer Network

Formal title: Introduction of two data flows for the Commissioning process for Half Hourly (HH) Supplier Volume Allocation (SVA) Current Transformer (CT) operated Metering Systems

Current Status

Submission
Assessment
CPC Consultation
Committee Decision
Awaiting Implementation
Implemented

Summary

Elexon has proposed to MRASCo that two new dataflows be introduced as part of the Metering System Commissioning process. The new dataflows will allow Licensed Distribution System Operators (LDSOs), Suppliers and Meter Operator Agents (MOAs) the ability to exchange information using the Data Transfer Network. CP1496 will allow those two dataflows to be reflected in Balancing and Settlement Code (BSC) Subsidiary Documents

Responsibility for Commissioning lies with the Registrant (normally a Supplier) however, this may be delegated to their MOA. The exception to this is measurement transformers. Where a measurement transformer is owned by a BSC Party (normally a LDSO), the BSC Party is responsible for Commissioning up to, and including, the testing facilities. Where a measurement transformer is owned by a non-BSC Party, the Registrant (via its MOA) is responsible for Commissioning. To meet these obligations, LDSOs e-mail Commissioning records as PDF attachments to MOAs. The MOAs then email any relevant PDF attachments to the Registrant notifying them of the Commissioning status of the Metering System. Where there are gaps in the process or issues with completing Commissioning, this information, and corresponding instructions, is also passed by email.

Passing information by email is resource intensive and is difficult to track for audit purposes. The introduction of two new dataflows will remove the need to use e-mail. We are also proposing changing the record keeping requirements so that whoever completes the Commissioning process will retain all records and make them available on request.

The Commissioning process, in reality, is different where the measurement transformers are owned by a BSC Party than where they are owned by a non-BSC Party. Timescales for omission and defect rectification are not given, so potentially inaccurate data from that Metering System could be used for Settlement for some time until defects are rectified. As such, CP1496 proposes separating the process for BSC Party owned and non-BSC Party owned measurement transformers as well as setting specific timescales to rectify defects or omissions.

Progression

CP1496 was presented to the ISG on 24 October and the SVG on 31 October for consideration. It was issued for consultation on 6 November until 1 December 2017. CP1496 will be presented to the ISG and SVG in January for decision.

CP1496 was approved by the ISG on 16 January 2018 and the SVG on 30 January 2018.

CP1496 was implemented on 1 November 2018 as part of the November 2018 BSC Release

Next Events

CP1496 was implemented on 1 November 2018 as part of the November 2018 BSC Release.

My BSC

Click on the X next to any of the icons to replace them with a short-cut link to the page you are currently on or search for a specific page.

List of BSC Insights

Previous Circulars

Training videos and services

Market Entry

Charge Codes and Switch Regimes

Add New

×

Or